Photo Update on Church Renovation

Finishing touches in August

As the date of the Dedication Mass approached, a miracle  unfolded before our eyes. Pews were quickly assembled and installed. Work continued on the brick veneer, and the two stained glass windows of Our Lady of the Assumption took their rightful place. The reredos was shrouded until opening day, only rarely revealed for adjustments. Outdoors, the planters and living landscape were made ready, and the patio was transformed from a work site to an outdoor living space.

July projects

Work is advancing rapidly on flooring in the nave of the church, framing the stained glass windows in dark wood, installation of paving blocks on the patio, painting inside and outside, and framing the church steps.

June projects

Crews are completing work on the tile roof after placement of an expansion joint at the peak. The cast was placed above the arch in preparation for a stained glass window. Inside crews are finishing interior walls, framing stained glass inside, and installing chandeliers. The reredos wall will be installed behind the altar as soon as it arrives from the port (shipment from Peru).  

 

 

May projects

Recent accomplishments include building planters in front, getting archway ready for veneer, installing HVAC ducting and equipment, and mezzanine stairs inside.

April projects

Recent accomplishments include pouring the concrete slab for the vestibule and framing the new vestibule, completing the north roof, finishing the outdoor canopy and seating, and breaking through the side of the church for a handicapped accessible reconciliation room. Excavation has begun on the front steps and planters.

March projects

The foundation for the vestibule has been poured, the trellis completed over patio and restroom entrances, Tiles are being installed on north side of roof, and fire sprinkler system is being installed. Designers consulted on  floor samples, wall tiles, countertops and upholstery fabric.

February projects

 Progress is being made on pouring footings for the patio and walkway behind the auditorium, beginning construction of the vestibule in front of church, completing the replacement of tiles on the roof, and moving the sanctuary steps forward in the church interior.

Photos from February Video

 

Late December and Week of Jan. 1-7

Installation of  steel beams supporting roof
Removal of central beam in church interior
Work on skylights and acoustical ceiling panels
Demo men's restroom and raise floor to altar level
Dig footings for patio cover
 

Week of Dec. 10-14

Breakthrough roof for interior lighting
Work on structural beams

Week of Dec. 3-7

Continue exterior roof construction
Demo exterior patio and walkways
Demo interior ceiling tiles
Move Mosaic Stations to expose windows
Remove church vestibule wall (interior)

Week of Nov. 26-30

Continue roof construction
Interior scaffolding
 

Week of Nov. 12-16

Interior abatement (no photos)
Demo front walkway
Remove roof tiles, etc.
 

Weekend of Nov. 10-11

Groundbreaking
First Masses in new worship place

Week of Nov. 5-9

Prepare new worship place

Week of Oct. 29-Nov. 2

Continue to re-locate liturgical objects
 

Week of Oct. 22-26

Move all furniture and articles out of church

Week of Oct. 15

Deacon Bob prepares video of old church interior with help of Claremont Heritage Foundation